TABLE OF CONTENTS
7. ENVIRONMENTAL
COMPLAINT AND NON-COMPLIANCE
8. IMPLEMENTATION
STATUS OF ENVIRONMENTAL MITIGATION MEASURES
FIGURES
Figure 1 Project
General Layout
Figure 2 Air
and Noise Monitoring Locations
LIST OF APPENDICES
Project Organization Chart |
|
Event Action Plans |
|
Waste Flow Table |
|
Environmental Mitigation
Implementation Schedule (EMIS) |
|
Weather and Meteorological
Conditions during Reporting Month |
|
Cumulative statistics on
Environmental Complaints, Notifications of Summons and Successful
Prosecutions |
|
Summary of Site Audit in the
Reporting Month |
|
Outstanding Issues and
Deficiencies |
|
Action and Limit Levels for Air
Quality and Noise |
|
|
|
i.
The Civil Engineering and Development
Department HKSAR has appointed MateriaLab Consultants Limited (MCL) to
undertake the Environmental Team services for the Project and implement the
EM&A works.
ii.
This Monthly EM&A report presents the
environmental monitoring and audit works for the period between 1 March and 18
March 2021. As informed by the Contractor, no major construction activities
were carried out in the reporting month.
Breaches of the Action and Limit Levels
iii. No Action / Limit Level exceedance was
recorded for 24-hr TSP at KTD1, KTD2c and KER1 in the reporting month.
iv. No Action / Limit Level exceedance was recorded
for construction noise at KTD1, KTD2c and KER1 in the reporting month.
Complaint, Notification of Summons and Successful Prosecution
v. No environmental complaint, notification of
summons and successful prosecution were received in the reporting month.
Reporting Changes
vi. The proposal for Termination of EM&A
Programme under this Contract was certified by the ET Leader, verified by the
IEC on 15 December 2020, approved by EPD on 18 March 2021. The construction
phase of EM&A programme has been terminated on 18 March 2021.
Future Key Issues
vii. There was no future key issues in the
reporting month.