TABLE OF CONTENTS
2. Summary
of EM&A Requirements and monitoring results
6. ENVIRONMENTAL
COMPLAINT AND NON-COMPLIANCE
7. IMPLEMENTATION
STATUS OF ENVIRONMENTAL MITIGATION MEASURES
FIGURES
Figure 1 Project General Layout
Figure
2 Air
and Noise Monitoring Locations
LIST
OF APPENDICES
|
|
i. The Civil Engineering and Development
Department HKSAR has appointed MateriaLab Consultants
Limited (MCL) to undertake the Environmental Team services for the Project and implement
the EM&A works.
ii. This is the First Quarterly EM&A
Report presents the environmental monitoring and audit works for the period
between 26 February 2016 and 31 May 2016. As informed by the Contractor, major
activities in the reporting period included:
February
- March 2016 |
April 2016 |
May 2016 |
· Setting up RE site office at Portion WA1; · Carrying out ground
investigation and pre-drilling; · Carrying out Condition Survey; · Construction of guide walls
at Zone 1; · Setting up Silo Tanks and Bentonite Pools for
SUS; · Construction of H piles at Zone 1; · Installation of ground
monitoring instruments at Zone 1; · Demolition of foundation at Zone
4; · Construction of hoarding
along Shing Fung Road
& Shing Cheong Road; · Setting up stockpiling
area for drying of slurry
and Bentonite at Portion E; and · Tree felling at Portion X. |
· Carrying out ground
investigation and pre-drilling; · Construction of guide walls
and D-walls at Zone 1; · Construction of H piles at Zone 1; · Construction of hoarding
along Shing Fung Road
& Shing Cheong Road; · Construction of garden
at Portion WA1; · Construction of temporary
manhole at Zone 1 as discharge
point; · Implementation of Temporary Traffic
Arrangement (TTA) along
Cheung Yip Street and Shing
Cheong Road; · Setting up wheel washing bay near
portion E; and · Setting up waste water treatment system at Zone 1. |
· Carrying out ground
investigation and pre-drilling; · Construction of guide walls
and D-walls at Zone 1 & Zone 2; · Construction of H piles at Zone 1; · Demolition of foundation at Zone
4; · Demolition of guard house at Zone
4; · Construction of temporary
drainage system at Zone 1; · Construction of subway
B; · Construction of hoarding
along Shing Fung Road, Shing Cheong Road & Cheung Yip Street; · Implementation of Temporary Traffic
Arrangement (TTA) along Cheung Yip
Street and Shing Cheong
Road; · Erection of scaffolding
at Radar Tower; and · Setting up waste water treatment system at Zone 4. |
Breaches of the Action and Limit Levels
iii.
Total 3 no. of
Action Level exceedances were recorded in the reporting period. Exceedances
were recorded for 24-hr TSP Action Levels at KTD1a and KTD2a on 1 March 2016
and at KTD2a on 30 March 2016. No Limit Level exceedance for 24-hr TSP and no
Action and Limit Level exceedance for construction noise were recorded in the
reporting period.
Complaint,
Notification of Summons and Successful Prosecution
iv.
No environmental
complaint and no notification of summons and successful prosecution were
received in the reporting period.